The main dates of the project

The main dates of the project are:

  • Endorsement by the Delegation of the European Commission: 23rd of December 2006
  • Notification to the partners: 4th of January 2006
  • Beginning of the project and arrival of the RTA: 5th of January 2006
  • Kick-Off meeting: 26th of January 2006
  • 1st Steering Committee meeting: 12th of April 2006
  • 2nd steering Committee meeting (common to the 9 twinning projects): 28th of April 2006
  • 3rd steering Committee meeting: 12th of July 2006

In detail the activities of the twinning (updated regularly)

acces extranet :